Western Australian mining lease

M 74/116 · Ravensthorpe - First Quantum

M 74/116 is a Western Australian mining lease held by FQM AUSTRALIA NICKEL PTY LTD (First Quantum Minerals group). Granted 6 May 1998, expires 6 May 2040. 968 ha in the Phillips River Mineral Field. Commodities: Nickel, Cobalt, Copper, Zinc. Part of the Ravensthorpe - First Quantum project (operating).

Type
Mining lease
Status
Granted
Holder
FQM AUSTRALIA NICKEL PTY LTD
Parent group
First Quantum Minerals (a joint venture)
MINEDEX project
Ravensthorpe - First Quantum J02145 · Operating
Owners: First Quantum Minerals Ltd 70%; Posco Holdings Inc 30%
Lodged
11 February 1998
Granted
6 May 1998
Expires
6 May 2040
Area
968.40 hectares (9.7 km²)
Mineral field
Phillips River Mineral Field
Commodities
Nickel, Cobalt, Copper, Zinc
Rehabilitation liability
Its rehabilitation liability is in the MCF Mining Index (subscribers): the Mining Rehabilitation Fund estimate, its trend since 2014, company provisions and closure-plan costs
Mine closure plan
RAVENTHORPE NICKEL OPERATIONS PTY LTD - MINERAL FIELD 74: approved 10 May 2016, MINE CLOSURE PLAN - RAVENTHORPE NICKEL OPERATIONS PTY LTD - MINERAL FIELD 74 - FEBRUARY 20
Environmental registrations
12 mining proposal and closure plan registrations (MINEDEX)
EPA referred proposals
Ravensthorpe Nickel Project Approved (Ministerial Statement), MS 633; overlaps 578 ha
WAMEX data
316 open-file drill holes, 60 exploration reports on this ground
Location
-33.68625, 120.38215 (centre)
Open on the mapAll mining leases

Mining proposals and mine closure plans

DateRegistrationTitleStatusDocument (GeoDocs)
6 June 2025Mining ProposalRNO Tailings Storage Facility Waste and LandfillApprovedMP_500203.pdf
5 April 2023Mining ProposalRavensthorpe Nickel Operation: Tailings Storage Facility 2 Stage 4 and 5 RaiseApprovedMP_114152.pdf
8 November 2021Mining ProposalRavensthorpe Nickel Operation: Tailings Storage Facility 2 Stage 3 RaiseApprovedno public document
10 May 2016Mine Closure PlanMINE CLOSURE PLAN - RAVENTHORPE NICKEL OPERATIONS PTY LTD - MINERAL FIELD 74 - FEBRUARY 2016Approvedmcp_58730.pdf
29 December 2015Mining ProposalFQMAN RNO Mining Proposal TSF wall raises Sept 2015Approvedmp_56253.pdf
13 August 2014Mining ProposalAmendment to MP40462 Hale Bopp to Include Southern Resouce Open Cut MiningApprovedmp_46154.pdf
8 November 2013Mining ProposalRavensthorpe Nickel Operations Pty Ltd - Mineral Field 74 - Mining Proposal - Hale Bopp Open Cut Pit on Mining Tenements M74/115, M74/116, M74/144 & M74/175Approvedmp_40462.zip
20 August 2013Mining ProposalAmendment to MP38188 - Expansion of Tailings Storage Facility at Ravensthorpe Nickel OperationsApprovedmp_40345.zip
12 April 2013Mining ProposalMining Proposal RNO Tailings Storage Facility ExpansionApprovedmp_38188.zip
27 April 2007Mining ProposalRAVENSTHORPE NICKEL/RNO/AMENDMENT TO PIPELINE-PUMP STATIONApprovedmp_5687.pdf
13 March 2007Mining ProposalRAVENSTHORPE NICKEL/RNO/AMENDMENT NOI SEAWATER PIPELINEApprovedmp_5649.zip
mp_5649.pdf
28 April 2004Mining ProposalRAVENSTHORPE - BANDALUP / NICKEL PLANT AND INFRASTRUCTUREApprovedmp_4549.pdf

Registrations from MINEDEX (DMPE); the documents are the operators' own, linked on GeoDocs and not copied.