Data as at 18 October 2026 · from Western Australian Government registers and open data
Western Australian mining lease
M 52/309 · Plutonic Gold
M 52/309 is a Western Australian mining lease held by CATALYST (PLUTONIC) PTY LTD (Catalyst Metals group). Granted 26 August 1992, expires 2 September 2034. 700 ha in the Peak Hill Mineral Field. Commodities: Gold, Silver. Part of the Plutonic Gold project (operating).
- Type
- Mining lease
- Status
- Granted
- Parent group
- Catalyst Metals (matched by name)
- MINEDEX projects
- Plutonic Gold J00417 · OperatingOwners: Catalyst Metals Ltd 100%; Dampier (Plutonic) Pty Ltd; Catalyst (Plutonic) Pty Ltd; Superior Gold Inc.
Hermes Gold J02253 · Care and MaintenanceOwners: Catalyst Metals Ltd 100%; Catalyst (Plutonic) Pty Ltd; Superior Gold Inc. - Lodged
- 10 May 1992
- Granted
- 26 August 1992
- Expires
- 2 September 2034
- Area
- 700.10 hectares (7.0 km²)
- Mineral field
- Peak Hill Mineral Field
- Commodities
- Gold, Silver
- Rehabilitation liability
- Its rehabilitation liability is in the MCF Mining Index (subscribers): the Mining Rehabilitation Fund estimate, its trend since 2014, company provisions and closure-plan costs
- Mine closure plan
- Hermes Mine Expansion on M52/685 and M52/797: approved 3 May 2019, Hermes Mine Expansion Mining Proposal on M52/685 and M52/797
Marymia Gold Mine - Plutonic Dome - VANMCP ( ): approved 3 November 2017, Mine Closure Plan Marymia Gold Mine - Plutonic Dome - VANMCP (Version 2)
Plutonic Gold Mine: approved 3 November 2015, Plutonic Gold Mine - Environmental registrations
- 6 mining proposal and closure plan registrations (MINEDEX)
- WAMEX data
- 58 open-file drill holes, 75 exploration reports on this ground
- Location
- -25.3382, 119.4409 (centre)
Mining proposals and mine closure plans
| Date | Registration | Title | Status | Document (GeoDocs) |
|---|---|---|---|---|
| 31 January 2019 | Mine Closure Plan | Mine Closure Plan - Plutonic Gold Mine - Version 3 | Approved | mcp_72068.pdf |
| 24 May 2018 | Mine Closure Plan | Mine Closure Plan - Hermes Gold Project M52/685, M52/797, L52/116, L52/164, L52/165, L52/166, M52/309, M52/150 & M52/149 - Version 4 | Approved | no public document |
| 3 November 2017 | Mine Closure Plan | Mine Closure Plan Marymia Gold Mine - Plutonic Dome - VANMCP (Version 2) | Approved | mcp_69388.pdf |
| 19 June 2017 | Mining Proposal | MINING PROPOSAL - Revised, Hermes Gold Project, Version 4, M52/685, M52/797, L52/116, L52/117, L52/164, M52/149, M52/150, M52/253, M52/309, M52/395, L52/165 & L52/166 | Approved | mp_64986.pdf |
| 15 December 2016 | Mining Proposal With Mine Closure Plan | Mining Proposal - Revised- Hermes Gold Project - Version 3 - M52/685, M52/797, L52/116, L52/117, L52/164, M52/149, M52/150, M52/253, M52/309 & M52/395 | Approved | mp_60472.pdf |
| 3 November 2015 | Mine Closure Plan | Plutonic Gold Mine | Approved | mcp_54714.pdf |
Registrations from MINEDEX (DMPE); the documents are the operators' own, linked on GeoDocs and not copied.
MCF Mining Approvals Index