Mining Capital FundsMCF Mining Approvals Index

Data as at 18 October 2026 · from Western Australian Government registers and open data

Western Australian mining lease

M 37/155 · Darlot

M 37/155 is a Western Australian mining lease held by DARLOT MINING COMPANY PTY LTD (Vault Minerals group). Granted 10 July 1988, expires 17 July 2030. 997 ha in the Mount Margaret Mineral Field. Commodities: Gold, Silver. Part of the Darlot project (operating).

Type
Mining lease
Status
Granted
Holder
DARLOT MINING COMPANY PTY LTD
Parent group
Vault Minerals (the MINEDEX project owner)
MINEDEX project
Darlot J00082 · Operating
Owners: Vault Minerals Limited 100%
Lodged
2 October 1987
Granted
10 July 1988
Expires
17 July 2030
Area
996.90 hectares (10.0 km²)
Mineral field
Mount Margaret Mineral Field
Commodities
Gold, Silver
Rehabilitation liability
Its rehabilitation liability is in the MCF Mining Index (subscribers): the Mining Rehabilitation Fund estimate, its trend since 2014, company provisions and closure-plan costs
Mine closure plan
DARLOT PROJECT: approved 6 February 2023, MINE CLOSURE PLAN - DARLOT PROJECT - J00082
DARLOT GOLD MINE: approved 20 June 2019, MINE CLOSURE PLAN - DARLOT GOLD MINE - J00082
Environmental registrations
25 mining proposal and closure plan registrations (MINEDEX)
WAMEX data
1,606 open-file drill holes, 88 exploration reports on this ground
Location
-27.88675, 121.278 (centre)
Open on the mapAll mining leases

Mining proposals and mine closure plans

DateRegistrationTitleStatusDocument (GeoDocs)
26 February 2025Mining ProposalDarlot Gold Mine Flood Diversion Drain & Abandonment Bund SOMPApprovedMP_500054.pdf
1 October 2024Mining ProposalDarlot Gold Mine Borrow Pit SOMPApprovedMP_127968.pdf
6 February 2023Mine Closure PlanMINE CLOSURE PLAN - DARLOT PROJECT - J00082ApprovedMCP_114639.pdf
10 March 2020Mining ProposalAddendum to Mining Proposal - Eldorado Pit Surface Water DrainsApprovedMP_85069.pdf
20 June 2019Mine Closure PlanMINE CLOSURE PLAN - DARLOT GOLD MINE - J00082Approvedmcp_69390.pdf
7 February 2019Mining ProposalProcess Plant Throughput Increase From 850ktpa to 1.2MtpaApprovedno public document
3 February 2017Mining ProposalPutrescible Landfill & Borrow Pit Extensions M37/252 & M37/155Approvedmp_62553.pdf
12 July 2016Mining ProposalAddendum to Mining Proposal Darlot Oxides & AlluvialsApprovedmp_59596.pdf
9 September 2014Mining ProposalMining Proposal - Airstrip Borrow Pit on M37/155Approvedmp_51011.pdf
28 November 2013Mining ProposalRecommissioning of TSF2 and Harvesting of Tails from TSF3 to Underground Cement Paste Fill (CPF) PlantApprovedmp_43679.pdf
20 May 2011Mining ProposalMP - Barrick Gold - Darlot Gold Mine TSF 4Approvedmp_27916.pdf
15 June 2006Mining ProposalDARLOT : PASTE FILL PLANT-HARVESTING OF TAILINGS M37/155 252Approvedmp_5276.pdf
29 May 2002Mining ProposalDARLOT: TAILINGS DAM 3Approvedmp_3916.pdf
6 June 2000Mining ProposalDARLOT INCREASED PLANT THROUGHPUTApprovedmp_16739.pdf
3 November 1998Mining ProposalDARLOT : WESTERN DEEP LEAD IN PIT TAILINGSApprovedmp_2895.pdf

10 earlier registrations are in MINEDEX.

Registrations from MINEDEX (DMPE); the documents are the operators' own, linked on GeoDocs and not copied.