M 24/266 · Paddington - Mt Pleasant

M 24/266 is a Western Australian mining lease held by PADDINGTON GOLD PTY LIMITED (Zijin Mining group). Granted 21 September 1988, expires 28 September 2030. 122 ha in the Broad Arrow Mineral Field. Commodities: Gold, Silver. Part of the Paddington - Mt Pleasant project (operating).

Type
Mining lease
Status
Granted
Holder
PADDINGTON GOLD PTY LIMITED
Parent group
Zijin Mining (a subsidiary)
MINEDEX projects
Paddington - Mt Pleasant J00292 · Operating
Owners: Norton Gold FIelds Pty Ltd 100%; Zijin Mining Group; Keras Resources Plc; Paddington Gold Pty LIMIted

Mt Pleasant Prospecting J02444 · Shut
Owners: a private holder 100%
Lodged
16 June 1988
Granted
21 September 1988
Expires
28 September 2030
Area
122.40 hectares (1.2 km²)
Mineral field
Broad Arrow Mineral Field
Commodities
Gold, Silver
Rehabilitation liability
Its rehabilitation liability is in the MCF Mining Index (subscribers): the Mining Rehabilitation Fund estimate, its trend since 2014, company provisions and closure-plan costs
Mine closure plan
Mount Pleasant: approved 12 April 2017, Mine Closure Plan Mount Pleasant
Environmental registrations
28 mining proposal and closure plan registrations (MINEDEX)
EPA referred proposals
Fire Management Strategies - track upgrading and chaining Not assessed; overlaps 122 ha
WAMEX data
1,202 open-file drill holes, 68 exploration reports on this ground
Location
-30.52975, 121.23775 (centre)
Open on the mapAll mining leases

Mining proposals and mine closure plans

DateRegistrationTitleStatusDocument (GeoDocs)
11 July 2024Mining ProposalMt Pleasant Operations Version 3.1ApprovedMP_123530.pdf
22 October 2021Mining ProposalMP for Small Mining Operations: Tuart Underground InfrastructureApprovedno public document
22 May 2018Mining ProposalMount Pleasant to Paddington Haul Road Realignment AddendumApprovedmp_73545.pdf
16 March 2018Mining ProposalPaddington Liberty and Stockyard Haul Road Mining Proposal - Version 1Approvedmp_72378.pdf
12 April 2017Mine Closure PlanMine Closure Plan Mount PleasantApprovedmcp_58989.pdf
16 February 2016Mining Proposal With Mine Closure PlanTuart Underground Mining Proposal Paddington Gold Pty Ltd M24/234, M24/265, M24/266, M24/302 and M24/82 February 2016Approvedmp_58503.pdf
1 April 2014Mining ProposalMount Pleasant Alternative Haul Road Mining ProposalApprovedmp_45713.pdf
10 September 2013Mining ProposalBlue Gum and Green Gum Cutback- Mining ProposalApprovedmp_40164.pdf
14 August 2012Mining ProposalGreen Gum Open Cut Mining Proposal (Version 2) - Paddington Gold Pty Ltd - M24/227, M24/265, M24/266 & M24/393 - July 2012Approvedmp_36086.pdf
24 March 2009Mining ProposalHOMESTEAD UNDERGROUND PROJECTApprovedmp_21248.pdf
16 August 2006Mining ProposalTIES DREAM: SCRAP AND DETECT M24/82 M24/266 M24/710 M24/557Approvedmp_5425_res.pdf
28 January 2005Mining ProposalMT PLEASANT PROSPECTING / WALLACE-KENT SCRAPE AND DETECTApprovedmp_4907.pdf
16 May 2001Mining ProposalMT PLEASANT : SURFACE WATER MANAGEMENTApprovedmp_3694.pdf
5 December 2000Mining ProposalMT PLEASANT : SURFACE WATER HARVESTINGApprovedmp_3554.pdf
8 August 2000Mining ProposalMT PLEASANT QUARTERS UNDERGROUND REVISEDApprovedmp_3385.pdf

13 earlier registrations are in MINEDEX.