Mining Capital FundsMCF Mining Approvals Index

Data as at 18 October 2026 · from Western Australian Government registers and open data

Western Australian mining project · Operating

Sunrise Dam

Sunrise Dam is a Western Australian mining project (operating) in MINEDEX, owned by Anglogold Ashanti Limited 100%, on 18 current tenements held by ANGLOGOLD ASHANTI AUSTRALIA LIMITED. Commodities: Gold, Silver.

MINEDEX project
J01703
Stage
Operating
Owners (MINEDEX)
Anglogold Ashanti Limited 100%
Tenement holders
ANGLOGOLD ASHANTI AUSTRALIA LIMITED
Parent groups
AngloGold Ashanti
Commodities
Gold, Silver
Rehabilitation liability
Its rehabilitation liability is in the MCF Mining Index (subscribers): the Mining Rehabilitation Fund estimate, its trend since 2014, company provisions and closure-plan costs

Resources and reserves

CommodityResourcesReservesLatest estimate
Gold85 Mt at 1.88 g/t, 5.13 Moz contained15 Mt at 2.01 g/t, 968 koz contained31 December 2024

Current MINEDEX estimates over all the project's sites; resources may include reserves. MINEDEX (DMPE), CC BY 4.0.

Mine closure plans

SiteOperatorLatest plan approvedPlan (PDF on GeoDocs)Closure year
Sunrise Dam GoldANGLOGOLD ASHANTI AUSTRALIA Limited22 February 20162014 Sunrise Dam Gold Mine Closure Plan
AngloGold Ashanti Aerodrome Critical Objects Scrub RollingANGLOGOLD ASHANTI AUSTRALIA Limited6 January 2017AngloGold Ashanti Aerodrome Critical Objects Scrub Rolling Mining Proposal - Version 2

EPA Ministerial Statements

MS 839 Tropicana Gold Project, MS 551 Wallaby Gold Mine Project

Tenements

TenementHolderStatusExpiresCommoditiesHectares
M 39/1116
Mining lease
ANGLOGOLD ASHANTI AUSTRALIA LIMITEDGranted18 July 2038Gold, Silver7,788
M 39/1117
Mining lease
ANGLOGOLD ASHANTI AUSTRALIA LIMITEDGranted18 July 2038Gold1,765
L 38/68
Miscellaneous licence
ANGLOGOLD ASHANTI AUSTRALIA LIMITEDGranted18 February 2027Gold109
L 38/93
Miscellaneous licence
ANGLOGOLD ASHANTI AUSTRALIA LIMITEDGranted21 November 2043Gold61
L 38/105
Miscellaneous licence
ANGLOGOLD ASHANTI AUSTRALIA LIMITEDGranted24 October 2027Gold, Silver649
L 38/176
Miscellaneous licence
ANGLOGOLD ASHANTI AUSTRALIA LIMITEDGranted20 July 2032Gold146
L 39/58
Miscellaneous licence
ANGLOGOLD ASHANTI AUSTRALIA LIMITEDGranted5 September 2030Gold129
L 39/59
Miscellaneous licence
ANGLOGOLD ASHANTI AUSTRALIA LIMITEDGranted16 October 2031Gold10
L 39/74
Miscellaneous licence
ANGLOGOLD ASHANTI AUSTRALIA LIMITEDGranted18 February 2027Gold556
L 39/210
Miscellaneous licence
ANGLOGOLD ASHANTI AUSTRALIA LIMITEDGranted20 September 2031Gold414
L 39/225
Miscellaneous licence
ANGLOGOLD ASHANTI AUSTRALIA LIMITEDGranted16 September 203549
L 39/226
Miscellaneous licence
ANGLOGOLD ASHANTI AUSTRALIA LIMITEDGranted15 October 2035Gold, Silver259
L 39/227
Miscellaneous licence
ANGLOGOLD ASHANTI AUSTRALIA LIMITEDGranted18 January 2036Gold150
L 39/228
Miscellaneous licence
ANGLOGOLD ASHANTI AUSTRALIA LIMITEDGranted16 September 203520
L 39/233
Miscellaneous licence
ANGLOGOLD ASHANTI AUSTRALIA LIMITEDGranted28 January 20368
L 39/234
Miscellaneous licence
ANGLOGOLD ASHANTI AUSTRALIA LIMITEDGranted28 January 203620
L 39/248
Miscellaneous licence
ANGLOGOLD ASHANTI AUSTRALIA LIMITEDGranted6 November 2037Gold5
L 39/275
Miscellaneous licence
ANGLOGOLD ASHANTI AUSTRALIA LIMITEDGranted24 October 2039Gold268