Data as at 18 October 2026 · from Western Australian Government registers and open data
Western Australian mining project · Operating
Newman Aggregate / Holcim
Newman Aggregate / Holcim is a Western Australian mining project (operating) in MINEDEX, owned by Holcim (Australia) Pty Ltd 100%, on 5 current tenements held by HOLCIM (AUSTRALIA) PTY LTD. Commodities: SD.
- MINEDEX project
- J00862
- Stage
- Operating
- Owners (MINEDEX)
- Holcim (Australia) Pty Ltd 100%
- Tenement holders
- HOLCIM (AUSTRALIA) PTY LTD
- Parent groups
- Holcim
- Commodities
- SD
- Rehabilitation liability
- Its rehabilitation liability is in the MCF Mining Index (subscribers): the Mining Rehabilitation Fund estimate, its trend since 2014, company provisions and closure-plan costs
Production recorded in MINEDEX
| Commodity | Latest year | That year | All recorded |
|---|---|---|---|
| Sand - undifferentiated | 1993 | 125 kt | 280 kt |
| Aggregate - coarse | 2000 | 16 kt | 156 kt |
Historical: the bulk extract's production records end in 2002.
Mine closure plans
| Site | Operator | Latest plan approved | Plan (PDF on GeoDocs) | Closure year |
|---|---|---|---|---|
| NEWMAN QUARRY - M52/59, G52/15, G52/18, G52/278 and L52/115 | Holcim (Australia) Pty LTD | 17 August 2023 | MINE CLOSURE PLAN - NEWMAN QUARRY - M52/59, G52/15, G52/18, G52/278 and L52/115 - REVISION |
Tenements
| Tenement | Holder | Status | Expires | Commodities | Hectares |
|---|---|---|---|---|---|
| M 52/59 Mining lease | HOLCIM (AUSTRALIA) PTY LTD | Granted | 11 May 2029 | SD | 24 |
| G 52/15 General purpose lease | HOLCIM (AUSTRALIA) PTY LTD | Granted | 5 November 2031 | SD | 8 |
| G 52/18 General purpose lease | HOLCIM (AUSTRALIA) PTY LTD | Granted | 21 March 2036 | SD | 10 |
| G 52/278 General purpose lease | HOLCIM (AUSTRALIA) PTY LTD | Granted | 23 October 2047 | SD | 2 |
| L 52/115 Miscellaneous licence | HOLCIM (AUSTRALIA) PTY LTD | Granted | 13 February 2032 | SD | 4 |