Minerals progressive rehabilitation and closure plan

PRCP-EPML00951013 · PACIFIC SILICA PTY LTD

PRC plan PRCP-EPML00951013-V1 for PACIFIC SILICA PTY LTD (EPML00951013), minerals. Current schedule final milestone 2040-12-10; 15 rehabilitation and improvement areas.

Environmental authority
EPML00951013
Holders
PACIFIC SILICA PTY LTD
Tenures
ML50064; ML50088; ML50140; ML50156
Plan versions
PRCP-EPML00951013-V1 (effective 2023-02-28)
Current schedule final milestone
2040-12-10
Areas in current schedule
15 · 209 ha

Schedule versions

VersionEffectiveFinal milestoneAreasDocument
1 (current)2023-02-282040-12-1015Schedule PDF

Rehabilitation and improvement areas

From the current schedule's tables. Land use categories are keyword groupings; the schedule's wording is shown beneath.

AreaActivitiesHectaresPost-mining land useFirst milestonePage
RA1rehabilitationExtractive area (pit 4, pit 3)13.8 haGrazingGrazingCommencement of first milestone:8
RA2rehabilitationOperational area- processing, sales pads, access roads42.5GrazingGrazing1/04/20459
RA3rehabilitationDryplant- Processing plant2.3GrazingGrazingCommencement of first milestone:10
RA4rehabilitationBeachmere Southern Buffer2GrazingGrazing1/12/202511
RA5rehabilitationExtraction area- Haul/mining perimeter2.1GrazingGrazing10/12/202612
RA6rehabilitationOperations- Pump station 1, haul road, electrical control room4.2GrazingGrazing1/04/203513
RA7rehabilitationPit 15, Pit 4, Pit 8 Extractive areas6.9Native ecosystemNative Ecosystem10/04/202314
RA8rehabilitationExtraction area- Dredge site North east2.4Native ecosystemNative ecosystem1/04/202715
RA9rehabilitationOperations area- Wetplant processing area17.7Native ecosystemNative ecosystem10/12/203716
RA10rehabilitationPit 1, Pit 4 & Pit 14 extractive area21.8Native ecosystemWater storage- Native ecosystem1/4/202417
RA11rehabilitationProcess water storage- pit 5, pit 19N, Pit 19S, Pit 1018.6Native ecosystemWater storage- Native ecosystem10/12/204518
RA12rehabilitationTemporary storage pit6.9Other10/12/204519
RA13rehabilitationExtraction area- Pit 3. Process water – Pits 2, 6 and Laterite Pit14.5Other1/04/202920
RA14rehabilitationExtraction area- Beachmere41.3Other10/12/203521
RA15rehabilitationOperations area11.7OtherTrees & shrubs10/12/203222