Minerals progressive rehabilitation and closure plan

PRCP-EPML00881213 · MINERAL PROJECTS PTY LTD

PRC plan PRCP-EPML00881213-V1 for MINERAL PROJECTS PTY LTD (EPML00881213), minerals. Current schedule final milestone 2028-04-30; 5 rehabilitation and improvement areas.

Environmental authority
EPML00881213
Holders
MINERAL PROJECTS PTY LTD; TABLELAND RESOURCES PTY LTD
Tenures
ML2810; ML2811; ML2831; ML2832; ML2833; ML2834
Plan versions
PRCP-EPML00881213-V1 (effective 2023-05-03)
Current schedule final milestone
2028-04-30
Areas in current schedule
5 · 6 ha

Schedule versions

VersionEffectiveFinal milestoneAreasDocument
1 (current)2023-05-032028-04-305Schedule PDF

Rehabilitation and improvement areas

From the current schedule's tables. Land use categories are keyword groupings; the schedule's wording is shown beneath.

AreaActivitiesHectaresPost-mining land useFirst milestonePage
RA1rehabilitationOld infrastructure areas0.35 haGrazingLow-intensity cattle grazingDuring 2021/2022 dry seasons6
RA2rehabilitationPit and portal (including void)0.57 haGrazingLow-intensity cattle grazingEnd of mine life7
RA3rehabilitationOld reprofiled area2.45 haGrazingLow-intensity cattle grazingEnd of mine life8
RA4rehabilitationSettling Dam and waste rock stockpile2.6 haGrazingLow-intensity cattle grazingEnd of mine life9
RA5rehabilitationOther areas including tracks0.3 haGrazingLow-intensity cattle grazingEnd of mine life10