Minerals progressive rehabilitation and closure plan
PRCP-EPML00352613 · GRAYMONT (NSW) PTY LTD
PRC plan PRCP-EPML00352613-V1 for GRAYMONT (NSW) PTY LTD (EPML00352613), minerals. Current schedule final milestone 2050-12-10; 10 rehabilitation and improvement areas.
- Environmental authority
- EPML00352613
- Holders
- GRAYMONT (NSW) PTY LTD
- Tenures
- ML50111
- Plan versions
- PRCP-EPML00352613-V1 (effective 2023-07-06)
- Current schedule final milestone
- 2050-12-10
- Areas in current schedule
- 10 · 36 ha
Schedule versions
| Version | Effective | Final milestone | Areas | Document |
|---|---|---|---|---|
| 1 (current) | 2023-07-06 | 2050-12-10 | 10 | Schedule PDF |
Rehabilitation and improvement areas
From the current schedule's tables. Land use categories are keyword groupings; the schedule's wording is shown beneath.
| Area | Activities | Hectares | Post-mining land use | First milestone | Page |
|---|---|---|---|---|---|
| RA1rehabilitation | Northern and north-eastern overburden dump (rehabilitated) | 8.66 | GrazingLow intensity grazing | RM6 will commence 1 January 2023. This is a continuation of current monitoring and | 6 |
| RA2rehabilitation | Northern overburden dump (to be rehabilitated) | 0.69 | GrazingLow intensity grazing | RM4 will commence 1 January 2023 | 7 |
| RA3rehabilitation | North-eastern overburden dump (to be rehabilitated) | 6.4 | GrazingLow intensity grazing | RM3 will commence 1 January 2031 | 8 |
| RA4rehabilitation | Former Sediment Dam C | 0.12 | GrazingLow intensity grazing | RM1 will commence 1 January 2040 | 9 |
| RA5rehabilitation | Plant, buildings, silos/bins, misc. scrap, laydown areas, small tanks, product stockpiles | 5.04 | GrazingLow intensity grazing | RM1 will commence 1 January 2037 | 10 |
| RA6rehabilitation | Residual void | 9.73 | Water, diversions and flood landformsWater storage | RM1 will commence 1 January 2039. RM3 (reshaping) to occur on 0.55 ha of the highwall | 11 |
| RA7rehabilitation | Roads | 2.35 | GrazingLow intensity grazing | RM3 will commence 1 January 2041 | 12 |
| RA8rehabilitation | Sediment dam A, Sediment Dam B, Sediment Dam D (to be retained) | 1.57 | Water, diversions and flood landformsWater storage | RM1 will commence 1 January 2040 | 13 |
| RA9rehabilitation | Fuel storage, HME parking area | 0.2 | GrazingLow intensity grazing | RM1 will commence 1 January 2040 | 14 |
| RA10rehabilitation | Workshop, office, sheds, roads and bridge (to be retained) | 1.61 | Infrastructure, industrial or residentialRetained infrastructure | 1/01/2049 | 15 |