Queensland Mining Approvals IndexMining Capital Funds

Data as at 14 September 2026 · from the Queensland EP Act public register

Coal environmental authority

EPVX00515113 · SPRINGSURE MINING PTY LIMITED

Coal environmental authority EPVX00515113 (SPRINGSURE MINING PTY LIMITED), Granted. 20 conditions indexed. No PRC plan.

Status
Granted
Holders
SPRINGSURE MINING PTY LIMITED
PRC plan
None
How it was read
Numbered conditions (OCR)
Register
Register record · Instrument PDF

Conditions

20 numbered conditions read from the current instrument. Page numbers link into the register PDF.

  1. A2

    The financial assurance is to remain in force until the administering authority is satisfied that no claim on the assurance is likely. Note: Where progressive rehabilitation is completed and acceptable to the administering authority, progressive reductions to the amount of financial assurance will be applicable where rehabilitation has been completed in accordance with the rehabilitation conditions specified in this environmental authority.

    page 3OCR textRehabilitation
  2. A3

    For exploration activities the environmental authority holder must comply with each of the standard environmental conditions contained in the Code of Environmental Compliance for Exploration and Mineral Development Projects (EM586), except Condition 13, which is replaced by the conditions of this authority.

    page 3OCR text
  3. A4

    lf there is any inconsistency between a standard environmental condition and an additional condition in this environmental authority, the additional condition prevails to the extent of any inconsistency. www.ehp.qld.gov.au ABN 46 640 294 485 Permit Environmental authority EPVX00515113 Agency interest: Land Condition | Condition number Bi The environmental authority holder must not carry out activities in a Category A or B Environmentally Sensitive Areas. Activities involving machinery must not be carried out within 1km of a Category A Environmentally Sensitive Areas.

    page 3OCR text
  4. B2

    Exploration Drilling Program — within 500m of any Category B Environmentally Sensitive Areas The environmental authority holder is authorised to carry out exploration mining activities on EPC1674 and MDL3002 within 500 metres of any Category B Environmentally Sensitive Areas in accordance with Table B1: Authorised disturbance within 500m of any Category B Environmentally Sensitive Areas and illustrated in Attachment 1 — Location of drill holes (EPC1674 and MDL3002) within 500m of any Category B Environmentally Sensitive Areas (ESA). Table B1: Authorised disturbance within 500m of any Category B Environmentally Sensitive Areas ea =o Maximum footprint of Maximum disturbance jrottation oF act | disturbance permitted authorised within 500m Activity Category B | for each activity within of Category B Environmentally Sensitive | 500m buffer of Category | Environmental Sensitive A B Environmentally . Area rea Fr Sensitive Area 625m’ per drill pad Exploration Drill Holes 15 200mm aa per drill 0.9375ha 10m? sumps __ i \ ee

    page 4OCR text
  5. B3

    | The environmental authority holder must avoid clearing mature trees when undertaking drilling | activities within 500m buffer of any Category B ESA.

    page 4OCR text
  6. B4

    | Seismic surveys | | The environmental authority holder is not authorised to undertake seismic surveying within the | 500m buffer of any Category B ESA.

    page 4OCR text
  7. B5

    Access tracks and roads Existing access and fence line tracks must be used when entering 500m buffer of any Category B | ESA. New tracks may only be constructed with approval of the administering authority.

    page 4OCR text
  8. B6

    | Tracks constructed within 500m buffer of any Category B ESA must be less than 3m in width. www.ehp.qid.gov.au ABN 46 640 294 485 Permit Environmental authority EPVX00515113

    page 4OCR text
  9. B7

    No clearing of trees for access tracks to boreholes will take place within the 500m buffer of any jee B ESA. _ . a |

    page 5OCR text
  10. B8

    Authorised track construction within the 500m buffer of any Category B ESA must involve only blade clearing of established vegetation.

    page 5OCR textBiodiversity
  11. B9

    Tracks should not be used when soil is saturated and prone to displacement or erosion by vehicle movement.

    page 5OCR textLand and soil
  12. B10

    Other land disturbance Activities must not include costeaning or bulk sampling.

    page 5OCR text
  13. B11

    All equipment such as earthmoving and drilling equipment must be used in a manner which prevents the spread of weeds and minimises unnecessary disturbance of topsoil and ground cover vegetation. ——

    page 5OCR textLand and soil, Biodiversity
  14. B12

    Prior to entering any area which is within the 500m buffer of any Category B ESA all vehicles, machinery and equipment must be washed down and hold a current Weed Hygiene Declaration.

    page 5OCR text
  15. B13

    Campsites must not be established within a Category B ESA or within the 500m buffer of any Category B ESA.

    page 5OCR text
  16. B14

    All waste must be removed and disposed of offsite.

    page 5OCR textWaste
  17. B15

    Burning of vegetation is not permitted.

    page 5OCR textBiodiversity
  18. B16

    Rehabilitation & reporting Rehabilitation of areas disturbed within the 500m buffer of a Category B ESA must commence as soon as practicable to the extent that erosion impacts are minimised, and be completed as soon as practicable but no longer than three (3) months after completion of the disturbance activity.

    page 5OCR textRehabilitation, Land and soil, Monitoring and reporting
  19. B17

    Rehabilitation must be undertaken in accordance with requirements of the Code of Environmental Compliance for Exploration and Mineral Development Projects (EM586), and to the satisfaction of the administering authority.

    page 5OCR textRehabilitation
  20. B18

    An annual report must be prepared each year and submitted with each annual return. The report must include a map identifying all exploration activities undertaken within 500m of any Category B ESA to date. The map is to clearly distinguish between proposed, completed and rehabilitated mining activities to demonstrate compliance with this environmental authority. \ www.ehp.qid.gov.au ABN 46 640 294 485 Permit Environmental authority EPVX00515113 Definitions Words and phrases used throughout this environmental authority are defined in the Definitions section of this authority. Where a definition for a term used in this environmental authority is sought and the term is not defined within this environmental authority, the definitions in the Code of Environmental Compliance for Exploration and Mineral Development Projects (EM586) and the definitions in the Environmental Protection Act 1994, its regulations and policies must be used. “authority” means environmental authority (mining activities) under the Environmental Protection Act 1994. “borehole” means either an artesian bore or a subartesian bore. “costeaning” The digging of a trench or pit across the seam or ore body for exposing, sampling and mapping of the ore body. “endangered regional ecosystem” means a regional ecosystem identified as endangered in the database maintained by the administering authority called ‘Regional ecosystem description database’ containing regional ecosystem numbers and descriptions. “environmental authority” means a licence or approval issued by the administrating authority under the Environmental Protection Act 1994. “environmental authority holder” means the holder of this environmental authority. “Environmentally Sensitive Areas (ESA)” refers to locations, however large or small, that have environmental values that contribute to maintaining biological diversity and integrity have intrinsic or attributed scientific, historical or cultural heritage value, or are important in providing amenity, harmony or sense of community. Refer to Appendix A of Code of Environmental Compliance for Exploration and Mineral Development Projects. “general waste” Schedule 12 of the Environmental Protection Regulation 2008 defines general waste as “means waste other than regulated waste”. Waste rock, overburden and the contents of tailings dams are not included in the definition of genera! waste for the purposes of these conditions. “progressive rehabilitation” means rehabilitation (defined below) undertaken progressively or a staged approach to rehabilitation as mining operations are ongoing. “rehabilitation processes” The measures and actions taken to achieve rehabilitation outcomes, including any or all of the following: - removing all unwanted infrastructure; - backfilling mine excavations (e.g. pits) and capping drill holes: - reshaping the land surface to a stable landform similar to that of surrounding undisturbed areas; - spreading of topsoil; - spreading seed or planting seedlings to promote revegetation; - benching ridge cuts and removing any overhanging material.

    page 5OCR textRehabilitation, Groundwater, Regulated structures, Waste, Land and soil, Biodiversity, Monitoring and reporting