EPVL02943215 · John Turner

Minerals environmental authority EPVL02943215 (John Turner), Granted. 6 conditions indexed. No PRC plan.

Status
Granted
Holders
John Turner; Paul Smyth
Tenures
ML100016
PRC plan
None
How it was read
Numbered conditions
Register
Register record · Instrument PDF

Conditions

6 numbered conditions read from the current instrument. Page numbers link into the register PDF.

  1. A1

    The environmental authority does not take effect until the grant of the tenure to the environmental authority holder, or until each environmental authority holder has become a holder, under the Mineral Resources Act 1989, of each of the relevant mining tenements.

  2. A2

    The conditions of this environmental authority are in force until a surrender of the authority is accepted pursuant to the Environmental Protection Act 1994.

  3. A3

    The environmental authority holder is to give the administering authority a financial assurance in the amount and form and at a time required by the administering authority. Schedule B - Land

  4. B2

    The holder of this environmental authority must not carry out activities within a category A or B Environmentally Sensitive Area (ESA). Activities may be carried out within 2km of a category A ESA and within 1km of a category B ESA, providing the activities do not impact upon environmental values of the ESA.

  5. B3

    The environmental authority holder must not cause a significant residual impact to any prescribed environmental matters as defined under the Environmental Offsets Act 2014.

    page 4Biodiversity
  6. B4

    Records demonstrating that each impact to a prescribed environmental matter did not, or is not likely to, result in a significant residual impact to that matter must be: (a) completed by an appropriately qualified person; and (b) kept for the life of the environmental authority. END OF PERMIT Attachments Code of Environmental Compliance for Mining Lease Projects _____________________________________________________________________________________________________________

    page 4Monitoring and reporting