Queensland Mining Approvals IndexMining Capital Funds

Data as at 14 September 2026 · from the Queensland EP Act public register

Minerals environmental authority

EPPR00585813 · RIBFIELD PTY. LTD.

Minerals environmental authority EPPR00585813 (RIBFIELD PTY. LTD.), Granted. 123 conditions indexed. No PRC plan.

Status
Granted
Holders
RIBFIELD PTY. LTD.; MIDDLEMOUNT COAL PTY LTD
PRC plan
None
How it was read
Numbered conditions
Register
Register record · Instrument PDF

Conditions

123 numbered conditions read from the current instrument. Page numbers link into the register PDF.

  1. A1

    Provide a financial assurance in the amount and form required by the administering authority prior to the commencement of activities proposed under this environmental authority.

  2. A2

    The financial assurance is to remain in force until the administering authority is satisfied that no claim on the assurance is likely. Note: Where progressive rehabilitation is completed and acceptable to the administering authority, progressive reductions to the amount of financial assurance will be applicable where rehabilitation has been completed in accordance with the acceptance criteria defined within this environmental authority.

    page 5Rehabilitation
  3. A3

    The conditions of this environmental authority are in force until a surrender of the authority is accepted pursuant to the Environmental Protection Act 1994. The conditions apply unless an amendment is approved pursuant to the Environmental Protection Act 1994.

  4. A4

    The environmental authority holder must develop and implement during the continuation of this authority, a program to ensure that all employees and contractors on site are aware of and comply with the relevant requirements for this authority. Maintenance of measures, plant and equipment

  5. A5

    The environmental authority holder must ensure: a) that all measures, plant and equipment necessary to ensure compliance with the conditions of this environmental authority are installed; b) that such measures, plant and equipment are maintained in a proper conditions; and c) that such measures, plant and equipment are operated in a proper manner. Monitoring

    page 5Monitoring and reporting
  6. A6

    Record, compile and keep for a minimum of five years all monitoring results required by this environmental authority and make available for inspection all or any of these records upon request by the administering authority.

    page 5Monitoring and reporting
  7. A7

    Where monitoring is a requirement of this environmental authority, ensure that a competent person(s) conducts all monitoring.

    page 5Monitoring and reporting
  8. A8

    All instruments, equipment and measuring devices used for measuring or monitoring in accordance with any condition of this approval must be calibrated, and appropriately operated and maintained. Permit Environmental authority EPPR00585813 Storage and handling of flammable and combustible liquids

    page 5Monitoring and reporting
  9. A9

    All flammable and combustible liquids must be contained within an on-site containment system and controlled in a manner that prevents environmental harm and maintained in accordance with the current version of AS 1940 - Storage and Handling of Flammable and Combustible Liquids.

  10. A10

    Spillage of all flammable and combustible liquids must be controlled in a manner that prevents environmental harm. Storage and handling of chemicals

  11. A11

    All chemicals must be contained within an on-site containment system and controlled in a manner that prevents environmental harm and maintained in accordance with the current version of the relevant Australian Standard.

  12. A12

    Spillage of all chemicals must be controlled in a manner that prevents environmental harm. Spill Kits

  13. A13

    An appropriate spill kit, personal protective equipment and relevant operator instructions/emergency procedure guides for the management of wastes and chemicals associated with the activity must be kept at the site, and in each vehicle used.

    page 6Waste
  14. A14

    Anyone operating under this approval must be trained in the use of the spill kit. Notification of Emergencies and Incidents

    page 6Monitoring and reporting
  15. A15

    All reasonable actions are to be taken to minimise environmental harm, or the risk thereof, resulting from any emergency, incident or circumstances not in accordance with the conditions of this environmental authority.

  16. A16

    The environmental authority holder must notify the administering authority as soon as reasonably practicable after becoming aware of any emergency or incident resulting in the release of contaminants, or which threatens the release of contaminants, not authorised to be caused under this environmental authority. Permit Environmental authority EPPR00585813

    page 6Monitoring and reporting
  17. A17

    The notification in condition (A7-2) must include, but not be limited, to the following: a)the environmental authority number and name of holder; b)the name and telephone number of the designated contact person; c)the location of the emergency or incident; d)the date and time of the release; e)the time the holder of the environmental authority became aware of the release; f) the estimated quantity and type of substance released; g)the suspected cause of the release; h) a description of the effects of the release including environmental harm and/or environmental nuisance caused, threatened, or suspected to be caused by the release; i) any sampling conducted or proposed, relevant to the emergency or incident; and j) immediate actions taken to prevent any further release and mitigate any environmental harm and/or environmental nuisance caused by the release.

    page 7Biodiversity, Monitoring and reporting
  18. A18

    Not more than fourteen (14) days following the initial notification of an emergency or incident, further written advice must be provided to the administering authority, including the following: a) results and interpretation of any samples taken and analysed; b) outcomes of actions taken at the time to prevent or minimise environmental harm or environmental nuisance; and c) proposed actions to prevent a recurrence of the emergency or incident. Definitions

    page 7Monitoring and reporting
  19. A19

    Words and phrases used throughout this environmental authority are defined in Schedule H - Definitions. Where a definition for a term used in this environmental authority is sought and the term is not defined within this environmental authority, the definitions in the Environmental Protection Act 1994, its Regulations and Environmental Protection Policies must be used. Schedule B - Air Dust nuisance

  20. B1

    Subject to Conditions B2 and B3 the release of dust and/or particulate matter resulting from the mining activity must not cause an environmental nuisance, at any sensitive or commercial place.

  21. B2

    When requested by the administering authority, dust and particulate monitoring must be undertaken within a reasonable and practicable timeframe nominated by the administering authority to investigate any complaint (which is neither frivolous nor vexatious nor based on mistaken belief in the opinion of the authorised officer) of environmental nuisance at any sensitive or commercial place, and the results must be notified within fourteen (14) days to the administering authority following completion of monitoring. Permit Environmental authority EPPR00585813

    page 7Air, Monitoring and reporting
  22. B3

    If the environmental authority holder can provide evidence through monitoring that the following limits are not being exceeded then the holder is not in breach of B1: a) Dust deposition of 120 milligrams per square metre per day, averaged over one month when monitored in accordance with AS 3580.10.1 Methods for sampling and analysis of ambient air - Determination of particulates - Deposited matter - Gravimetric method of 1991; and b) A concentration of particulate matter with an aerodynamic diameter of less than 10 micrometre (-m) (PM10) suspended in the atmosphere of 150 micrograms per cubic metre over a 24 hour averaging time, at a sensitive or commercial place downwind of the operational land, when monitored in accordance with: i) Particulate matter - Determination of suspended particulate PM10 high-volume sampler with size-selective inlet - Gravimetric method, when monitored in accordance with AS 3580.9.6 Methods for sampling and analysis of ambient air - Determination of suspended particulate matter - PM (sub) 10 high volume sampler with size-selective inlet - Gravimetric method of 1990; and ii) Any alternative method of sampling PM10, which may be permitted by the `Air Quality Sampling Manual' as published from time to time by the administering authority.

    page 8Air, Monitoring and reporting
  23. B4

    If monitoring indicates exceedence of the relevant limits in Condition B3, then the environmental authority holder must investigate whether the exceedance is due to emissions of dust from the activity. If the mining activity is found to be the cause of the exceedance then the environmental authority holder must: a) address the complaint including the use of appropriate dispute resolution if required; and b) immediately implement dust abatement measures so that emissions of dust from the activity do not result in further environmental nuisance. Odour Nuisance

    page 8Air, Monitoring and reporting
  24. B5

    Subject to requirement of condition B6, the release of noxious or offensive odour(s) or any other noxious or offensive airborne contaminant(s) resulting from the mining activity must not cause an environmental nuisance at any sensitive or commercial place.

  25. B6

    When requested by the administering authority, odour monitoring must be undertaken within a reasonable and practicable timeframe nominated by the administering authority to investigate any complaint (which is neither frivolous nor vexatious nor based on mistaken belief in the opinion of the authorised officer) of environmental nuisance at any sensitive or commercial place, and the results must be notified within fourteen (14) days to the administering authority following completion of monitoring. Schedule C - Water Authorised Releases

    page 8Air, Monitoring and reporting
  26. C1

    Process water and storm water contaminated by mining activities must only be released to surface waters at the authorised release points as defined in Schedule C - Table 1 (Discharge Location) and in compliance with the release limits listed in Schedule C - Table 2 (End of pipe contaminant release limits). Permit Environmental authority EPPR00585813 Schedule C - Table 1 (Discharge Location) Authorised Discharge Latitude (GDA94) Longitude (GDA94) Location Point Discharge Point 1 668,384.00 7,470,227.78 Roper Creek (SE corner)

    page 8Surface water
  27. C2

    End of pipe release limits for process water and storm water contaminated by mining activities must be monitored at the locations and frequencies defined in Schedule C - Table 3 (End of pipe monitoring location and frequency) and comply with the contaminant limits defined in Schedule C - Table 2 (End of pipe contaminant release limits). Schedule C - Table 2 (End of pipe contaminant release limits) Contaminant Limits Quality characteristics Units Minimum Maximum pH pH units 6.5 8.5 Electrical Conductivity s.cm-1 N/A 1,500 Total Suspended Solids mg/L N/A 50 Dissolved Oxygen % 85 - Total Petroleum g/L - 0 Hydrocarbons (C6-C9) Total Petroleum g/L - 0 Hydrocarbons (C10-C36)

    page 9Monitoring and reporting
  28. C3

    Monitoring must be undertaken and records kept of a monitoring program of contaminant releases to Roper Creek at the monitoring points specified in Schedule C - Table 3 (End of pipe monitoring location and frequency), and for the parameters specified in Schedule C - Table 2 (End of pipe contaminant release limits). Schedule C - Table 3 (End of pipe monitoring location and frequency) Monitoring Point Latitude (GDA94) Longitude (GDA94) Frequency Monitoring Point 1 668,384.00 7,470,227.78 Daily during discharge (Release from Discharge Point 1)

    page 9Monitoring and reporting
  29. C4

    Authorised releases of process water and storm water contaminated by mining activities to Roper Creek in accordance with conditions C1, C2 and C3 shall be only during periods of natural flow events. The duration of a natural flow event shall not be extended as a consequence of the mine water release. Permit Environmental authority EPPR00585813

  30. C5

    The authority holder must, within twenty-eight (28) days of a water release, provide a report to the administering authority detailing: a) the reason for the release; b) the location of the release; c) all water quality monitoring results; d) any general observations; e) all calculations; and f) any other matters pertinent to the water release event.

    page 10Monitoring and reporting
  31. C6

    In addition to the quality characteristic limits specified in Schedule C Table 2 (End of pipe contaminant release limits), process water and storm water contaminated by mining activities released in accordance with conditions C1, C2, C3 and C4 must not have any properties nor contain any organisms or other contaminants in concentrations that are capable of causing environmental harm. Impacted Sites

  32. C7

    Waters must be monitored at the locations and frequency defined in Schedule C - Table 4 (Receiving water monitoring locations and frequency) for the parameters in Schedule C - Table 5 (Receiving water contaminant trigger levels). Schedule C - Table 4 (Receiving water monitoring locations and frequency) Sampling location Latitude Longitude (GDA94) Monitoring frequency (GDA94) Impacted sites (Receiving waters) Monitoring Point 2 671,455.26 7,469,020.12 Daily during flow Reference sites Monitoring Point 3 668,378.91 7,473,143.74 Daily during flow Monitoring Point 4 667,626.99 7,471,028.80 Daily during flow Monitoring Point 5 667,484.34 7,470,194.82 Daily during flow Permit Environmental authority EPPR00585813

    page 10Surface water, Monitoring and reporting
  33. C8

    If water quality of the `impacted sites' during authorised release and non-release flow events outlined in Schedule C - Table 4 (Receiving water monitoring locations and frequency), exceed any of the contaminant trigger levels stated in Schedule C - Table 5 (Receiving water contaminant trigger levels), the environmental authority holder must: a) complete an investigation in accordance with the ANZECC (2000) methodology, into the potential for environmental harm; and b) provide a written report to the administering authority within twenty-eight (28) days of the date of the original exceedence, outlining: i) details of the investigations carried out; and ii) actions taken to prevent environmental harm. Permit Environmental authority EPPR00585813 Schedule C - Table 5 (Receiving water contaminant trigger levels) Parameter Unit Trigger Levels Limit Type pH pH units < 6.0 - > 8.5 Minimum/Maximum Electrical Conductivity scm-1 80th percentile of reference1 or Maximum 1,500 scm-1 whichever is higher Total Suspended Solids mg/L 80th percentile of reference1 or Maximum 50 mg/L whichever is higher Aluminium (dissolved) g/L 27 Maximum Ammonia (dissolved) g/L 320 Maximum Antimony (dissolved) g/L 0.05 Maximum Arsenic (As III) (dissolved) g/L 1 Maximum Boron (dissolved) g/L 90 Maximum Cadmium (dissolved) g/L 0.06 Maximum Chromium (CrVI) (dissolved) g/L 0.01 Maximum Copper (dissolved) g/L 1 Maximum Iron (dissolved) g/L 0.01 Maximum Lead (dissolved) g/L 1 Maximum Manganese (dissolved) g/L 1200 Maximum Molybdenum (dissolved) g/L 0.01 Maximum Nickel (dissolved) g/L 8 Maximum Nitrate (NO3) g/L 4900 Maximum Petroleum Hydrocarbons Maximum g/L 0.01 (C6-C9)

    page 11Surface water, Monitoring and reporting
  34. C9

    The following information must be recorded in relation to all water sampling: a) the date on which the sample was taken; b) the time at which the sample was taken; c) the monitoring point at which the sample was taken; d) the measured or estimated daily flow of water contaminated by mining activities at the time of sampling; and e) the results of all monitoring.

    page 13Monitoring and reporting
  35. C10

    The method of water sampling required by this environmental authority must comply with that set out in the latest edition of the Environmental Protection Agency's Water Quality Sampling Manual. Sewage Treatment

  36. C11

    The daily operation of the sewage treatment plant and pollution control equipment must be carried out by a person(s) with appropriate experience and/or qualifications to ensure the effective operation of that treatment system and control equipment.

  37. C12

    Pipelines and fittings associated with the sewage treatment plant must be clearly identified. Lockable valves or removable handles must be fitted to all release pipelines situated in public access areas.

  38. C13

    Treated effluent from the sewage treatment plant must only be discharged from the authorised discharge point, as specified in Schedule C - Table 6 (Effluent discharge locations). Schedule C - Table 6 (Effluent discharge locations) Authorised Discharge Points Location Discharge Point 2 Sewage Treatment Plant Holding Tank

  39. C14

    Treated effluent must not be released to land.

  40. C15

    Treated effluent must not be released from the site to any waters or the bed and banks of any waters.

  41. C16

    Water or storm water contaminated by sewage treatment activities must not be released to any waters or the bed and banks of any waters. Permit Environmental authority EPPR00585813

  42. C17

    If the responsibility of the treated effluent is given or transferred to another person: a) the responsibility of such effluent must only be given or transferred in accordance with a written agreement (the third party agreement); b) include in the third party agreement a commitment from the person utilising the effluent to use effluent in such a way as to prevent environmental harm or public health incidences and specifically make the persons aware of the General Environmental Duty (GED) under section 319 of the Environmental Protection Act 1994, environmental sustainability of any effluent disposal and protection of environmental values of waters; and c) upon being notified or otherwise becoming aware that the person's use of effluent is causing or threatens to cause environmental harm or is posing a human health risk, and if the person does not rectify the situation upon written request, the giving and transferring responsibility for such effluent must cease.

    page 14Monitoring and reporting
  43. C18

    Biosolids produced by the activity for re-use must be: a) sampled, analysed, graded and classified according to the procedures specified in the administering authorities systems and standards; and b) re-used under a Transitional Environmental Program or other Environmentally Relevant Activity with the administering authorities approval. Sediment contaminant levels

    page 14Land and soil
  44. C19

    All reasonable and practicable erosion protection measures and sediment control measures must be implemented and maintained to minimise erosion and the movement of sediment including: a) all clean drainage waters, from undisturbed areas, kept separate from dirty waters from disturbed areas; b) water from disturbed catchments diverted into the mine water management system and sedimentation dams; c) sedimentation dams designed to contain a 6 hour, 10 year average recurrence interval rainfall event; and d) sediment shall be excavated from sediment dams as required to maintain design capacity. Permit Environmental authority EPPR00585813 Water and stormwater management

    page 14Surface water, Regulated structures, Land and soil
  45. C20

    A water management, erosion and sediment control plan must be prepared and implemented prior to commencement of activities on mineral development licence 282 and must include a site water balance indicating sources and quality of water for mineral development activities use as well as identifying methods to: a) manage recycling, reuse and treatment; b) manage contaminants; c) manage stormwater and on site water flows; d) develop and implement a system for emergency spills or discharges; e) separate clean water from undisturbed areas and water from disturbed areas; f) separate and process hydrocarbons and washdown water from other surface water sources; g) design and monitor sediment detention structures; h) design and monitor mine water dams; i) manage off site water releases and minimise sediments and salinity releases; j) ensure protection of the environmental values of the receiving waters downstream as it relates to the activity; k) incorporate a risk management approach to how changing levels of floods, drought and water quality risks should be addressed; l) minimize the potential for soil and spoil erosion, soil contamination and acid rock drainage, particularly with regard to first flush flows following rainfall events; and m) review and monitor the water management system, hydrological processes performance indicators and sediment retention pond capacities. Schedule D - Noise and Vibration 1.1.1.1 Noise Nuisance

    page 15Surface water, Regulated structures, Noise and vibration, Land and soil, Monitoring and reporting
  46. D1

    Subject to Conditions D2 and D3 noise from the mining activity must not cause an environmental nuisance, at any sensitive or commercial place.

    page 15Noise and vibration
  47. D2

    When requested by the administering authority, noise monitoring must be undertaken within a reasonable and practicable timeframe nominated by the administering authority to investigate any complaint (which is neither frivolous nor vexatious nor based on mistaken belief in the opinion of the authorised officer) of environmental nuisance at any sensitive or commercial place, and the results must be notified within fourteen (14) days to the administering authority following completion of monitoring. Permit Environmental authority EPPR00585813

    page 15Noise and vibration, Monitoring and reporting
  48. D3

    When requested by the administering authority, noise monitoring must be undertaken to investigate any compliant of noise nuisance, and the results notified within fourteen (14) days to the administering authority. Monitoring must include: a) LA 10, adj, 10 mins b) LA 1, adj, 10 mins c) the level and frequency of occurrence of impulsive or tonal noise; d) atmospheric conditions including wind speed and direction; e) effects due to extraneous factors such as traffic noise; and f) location date and time of recording.

    page 16Noise and vibration, Monitoring and reporting
  49. D4

    If monitoring indicated exceedance of the limits in Schedule D - Table 1 (Noise Limits), then the environmental holder must: a) address the complaint including the use of appropriate dispute resolution if required; and b) immediately implement noise abatement measures so that emissions of noise from the activity do not result in further environmental nuisance. Schedule D - Table 1 (Noise Limits) Noise level Monday to Saturday Sundays and Public Holidays dB(A) 7am - 6pm 6pm - 10pm 10pm - 7am 9am - 6pm 6pm - 10pm 10pm - 9am measured as Noise measured at a 'Noise sensitive place' LA10, adj, 10 mins B/g + 5 B/g + 5 B/g + 3 B/g + 5 B/g + 5 B/g + 0 LA1, adj, 10 mins B/g + 10 B/g + 10 B/g + 5 B/g + 10 B/g + 10 B/g + 5 Noise measured at a 'Commercial place' LA10, adj, 10 mins B/g + 10 B/g + 10 B/g + 5 B/g + 10 B/g + 10 B/g + 5 LA1, adj, 10 mins B/g + 15 B/g + 15 B/g + 10 B/g + 15 B/g + 15 B/g + 10 Note: Background (B/g)

    page 16Noise and vibration, Monitoring and reporting
  50. D5

    The method of measurement and reporting of noise levels must comply with the latest edition of the Environmental Protection Agency's Noise Measurement Manual. Permit Environmental authority EPPR00585813 1.1.1.2 Airblast Overpressure Nuisance

    page 16Noise and vibration, Monitoring and reporting
  51. D6

    Subject to conditions D7 and D8, the airblast overpressure level from blasting operations on the premises must not exceed the limits defined in Schedule D - Table 2 (Airblast Overpressure Level) at any sensitive place. Schedule D - Table 2 (Airblast Overpressure Level) Location Airblast Overpressure Measured Sensitive or commercial place Air blast overpressure level of 115 db (Linear peak) for nine (9) out of ten (10) consecutive blasts initiated and not greater than 120 db (Linear peak) at any time.

    page 17Noise and vibration
  52. D7

    When requested by the administering authority, airblast overpressure monitoring must be undertaken within a reasonable and practicable timeframe nominated by the administering authority to investigate any complaint (which is neither frivolous nor vexatious nor based on mistaken belief in the opinion of the authorised officer) of environmental nuisance at any sensitive or commercial place, and the results must be notified within fourteen (14) days to the administering authority following completion of monitoring.

    page 17Noise and vibration, Monitoring and reporting
  53. D8

    Airblast overpressure monitoring must include the following descriptors, characteristics and conditions: a) location of the blast(s) within the mining area (including which bench level); b) atmospheric conditions including temperature, relative humidity and wind speed and direction; and c) location, date and time of recording.

    page 17Noise and vibration, Monitoring and reporting
  54. D9

    If monitoring indicates exceedence of the relevant limits in Schedule D - Table 2 (Airblast Overpressure Level), then the environmental authority holder must: a) address the complaint including the use of appropriate dispute resolution if required; and b) immediately implement airblast overpressure abatement measures so that airblast overpressure from the activity does not result in further environmental nuisance.

    page 17Noise and vibration, Monitoring and reporting
  55. D10

    The method of measurement and reporting of airblast overpressure levels must comply with the latest edition of the Environmental Protection Agency's Noise Measurement Manual. 1.1.1.3 Vibration nuisance

    page 17Noise and vibration, Monitoring and reporting
  56. D11

    Subject to Conditions D12 and D13 vibration from the mining activity must not cause an environmental nuisance, at any sensitive or commercial place.

    page 17Noise and vibration
  57. D12

    When requested by the administering authority, vibration monitoring must be undertaken within a reasonable and practicable timeframe nominated by the administering authority to investigate any complaint (which is neither frivolous nor vexatious nor based on mistaken belief in the opinion of the authorised officer) of environmental nuisance at any sensitive or commercial place, and the results must be notified within fourteen (14) days to the administering authority following completion of monitoring.

    page 17Noise and vibration, Monitoring and reporting
  58. D13

    Vibration monitoring must include the following descriptors, characteristics and conditions: Permit Environmental authority EPPR00585813 a) location of the blast(s) within the mining area (including which bench level); b) atmospheric conditions including temperature, relative humidity and wind speed and direction; and c) location, date and time of recording.

    page 17Noise and vibration, Monitoring and reporting
  59. D14

    If monitoring indicates exceedence of the relevant limits in Schedule D - Table 3 (Vibration Limits), then the environmental authority holder must: a) address the complaint including the use of appropriate dispute resolution if required; and b) immediately implement vibration abatement measures so that vibration from the activity does not result in further environmental nuisance. Schedule D - Table 3 (Vibration Limits) Location Vibration measured Sensitive or commercial place 5 mm/s peak particle velocity for nine (9) out of ten (10) consecutive blasts and not greater than 10 mm/s peak particle velocity at any time Note: The method of measurement and reporting of vibration levels must comply with the latest edition of the Environmental Protection Agency's vibration and air blast overpressure monitoring guideline. Permit Environmental authority EPPR00585813 Schedule E - Waste Management Waste Management Plan

    page 18Noise and vibration, Waste, Monitoring and reporting
  60. E1

    A Waste Management Plan, in accordance with the waste management hierarchy and waste management principles of the Environmental Protection (Waste Management) Policy 2000, must be implemented prior to commencement of activities and maintained. The Waste Management Plan must include: a) waste management practices that will ensure that recyclables are diverted from landfill; b) procedures for identifying and implementing opportunities to improve the waste management practices employed including information and education packages for waste generators to assist in maximising the diversion of recyclable materials from landfill; c) details of any accredited management system employed, or planned to be employed, to implement the waste management practices; d) procedures for dealing with accidents, spills and other incidents that may impact on the waste management; e) disposal procedures for hazardous wastes; f) procedures for auditing waste loads to identify material to be removed for recycling; g) how often the performance of the waste management practices will be assessed (at least annually); h) the indicators or other criteria, taking into account economic, social and environmental factors on which the performance of the waste management practices will be assessed; i) training programs and guidance for waste transport contractors in the identification and source separation of recyclable materials; and j) a staff awareness and induction program that encourages re-use and recycling. Waste Storage

    page 19Waste
  61. E2

    Waste is not permitted to be disposed of within mineral development licence 282.

    page 19Waste
  62. E3

    General waste may be temporarily stored on mineral development licence 282 before being directed to a facility that can lawfully accept such waste.

    page 19Waste
  63. E4

    The following regulated waste may be temporarily stored on mineral development licence 282 before being directed to a facility that can lawfully accept such waste: a) tyres; b) batteries; c) hydrocarbons d) oils; e) oil interceptor sludges; f) oil water emulsions and mixtures; and g) chemicals listed under Schedule 7 of the Environmental Protection Regulation 1998.

    page 19Waste
  64. E5

    A designated area or storage containers must be set aside for the laydown and segregation of wastes.

    page 19Waste
  65. E6

    An effective fire break must be provided and maintained around all waste laydown areas. Permit Environmental authority EPPR00585813

    page 19Waste
  66. E7

    All reasonable and practicable fire prevention measures must be implemented, including removal of grass and other materials within a 10m radius of the scrap tyre storage area.

  67. E8

    Waste must not be burned or allowed to be burned on mineral development licence unless by approval of the administering authority.

    page 20Waste
  68. E9

    Waste batteries must be stored: a) in a bunded and roofed area; or b) palletised and plastic wrapped.

    page 20Waste
  69. E10

    A record of all wastes must be kept detailing the following information: a) date of pickup of waste; b) description of waste; c) quantity of waste; d) origin of the waste; and e) destination of the waste. Note: Trackable wastes as listed in Schedule 1 of the Environmental Protection (Waste Management) Regulation 2000 are not covered by this condition. Trackable wastes have similar recording requirements to this condition in accordance with a waste tracking system established under the above Regulation.

    page 20Waste, Monitoring and reporting
  70. E11

    All regulated waste removed from the site must be removed by a person who holds a current approval to transport such waste under the provisions of the Environmental Protection Act 1994.

    page 20Waste
  71. E12

    Each container of regulated waste must be marked to identify the waste contained therein. Schedule F - Land Rehabilitation

    page 20Rehabilitation, Waste
  72. F1

    All areas significantly disturbed by the mineral development activities must be rehabilitated to a stable landform with a self-sustaining vegetation cover in accordance with Schedule F - Table 1 (Final Land Use and Rehabilitation) and Schedule F - Table 2 (Landform Design Criteria). Permit Environmental authority EPPR00585813 Schedule F - Table 1 (Final Land Use and Rehabilitation) Disturbance Disturbance Pre-mine land Post-mine land Pre-mine land Post-mine land Reference site Type area (ha) identification Elevated 28 description suitability description suitability suitability landforms Land adjacent to MDL282 15 classification classification on L3 RP904207 Voids 22 described as Cattle grazing on Self-sustaining Land Suitability Self-sustaining 666,684.6E Disturbed by 7,471,091.4N (which is Infrastructure cleared and recreated landscape Classification recreated landscape representative of three however differing native vegetation remains at partially cleared that is populated with Class 2, 3 and 4. that is populated with communities within the approximate area). original land. Native native species. native species. N/A. Rehabilitated land contour. will have unique features. pastures and Adjacent land although improved pasture species mix may be different. species are established. As above Water filled voids to Land Suitability Water filled voids. As above. complement Classification conservation Class 2, 3 & 4. requirements of migratory species. Land Suitability Self- sustaining Self-sustaining native Classification recreated landscape vegetation. Class 2, 3 and 4. that is populated with native species. Permit Environmental authority EPPR00585813 Schedule F - Table 2 (Landform Design Criteria) Disturbance Maximum Vertical Height (m) Maximum Length Projective Surface Type Slope Range (m) Range Area (ha) Range Elevated 28 Landforms 10-15% 20-22 133-220 Infrastructure Areas <5% 26-28 520-900 22 Voids 53 degrees 60 75 15

    page 20Rehabilitation, Biodiversity
  73. F2

    Progressive rehabilitation must commence within six (6) months of operations ceasing within an area.

    page 22Rehabilitation
  74. F3

    A Rehabilitation Management Plan must be prepared and implemented by 31 October 2008 for the activities on mineral development licence 282 and must include: a) proposed acceptance criteria to meet the outcomes in Schedule F - Table 1 (Final Land Use and Rehabilitation) and Schedule F - Table 2 (Landform Design Criteria); b) a description of end of mine landform design and post mining land uses across the mine; c) details of the rehabilitation methods to be applied; d) the success criteria for rehabilitated land; e) identify the reference sites to be used to develop the rehabilitation success criteria; f) detailed future rehabilitation actions to be completed; g) landform design criteria including end of mineral development design; h) details on how landform design will be consistent and integrated with the surrounding topography; i) a description of rehabilitation monitoring and maintenance requirements to be applied to all areas of disturbance; j) a cost benefit analysis/triple bottom line assessment of the proposed final landform design criteria and alternatives; and k) the identification of potential problems and how they will be addressed. Voids

    page 22Rehabilitation, Monitoring and reporting
  75. F4

    Residual voids must not cause any serious environmental harm to land, surface waters or any recognised groundwater aquifer, other than the environmental harm constituted by the existence of the residual void itself and subject to any other condition within this environmental authority.

    page 22Groundwater, Surface water
  76. F5

    Complete an investigation into residual voids and submit a report to the administering authority proposing acceptance criteria to meet the outcomes in Condition F4 by 31 October 2008. Permit Environmental authority EPPR00585813 Infrastructure

    page 22Monitoring and reporting
  77. F6

    All infrastructure constructed by or for the environmental authority holder during the mining activities including water storage structures, must be removed from the site prior to mineral development licence surrender, except where agreed in writing by the post mining land owner/holder. Contaminants

  78. F7

    Contaminants must not be released to land in manner which constitutes nuisance, material or serious environmental harm. Exploration Drilling

  79. F8

    The environmental authority holder is authorised to undertake no more than eighteen (18) drill holes within Endangered Regional Ecosystems.

  80. F9

    The environmental authority holder is authorised to undertake no more than two hundred and twenty seven (227) drill holes within the 500m buffer of Endangered Regional Ecosystems.

  81. F10

    The environmental authority holder is authorised to undertake no more than sixty three (63) metres of Seismic Lines within Endangered Regional Ecosystems.

  82. F11

    The environmental authority holder is authorised to undertake no more than two thousand five hundred and thirty eight (2,538) metres of Seismic Lines within the 500m buffer of Endangered Regional Ecosystems.

  83. F12

    In carrying out mining activities on MDL 282 all reasonable and practicable measures must be taken to prevent or minimise the likelihood of environmental harm being caused to Endangered Regional Ecosystems.

  84. F13

    Mining activities undertaken must be consistent with the `Middlemount Bulk Sample Operation - Environmental Management Plan, 09 October 2008'.

  85. F14

    When carrying out mining activities within any Endangered Regional Ecosystems and the 500m buffer of Endangered Regional Ecosystem, the holder of the environmental authority must do so in accordance with conditions F15 - F32. Drilling or Seismic Grid

  86. F15

    Spacing of gridlines within the Endangered Regional Ecosystems may only be undertaken at minimal intervals of 200m.

  87. F16

    Drill site intensity is limited to four sites per hectare within Endangered Regional Ecosystems or the 500m buffer of Endangered Regional Ecosystems.

  88. F17

    The operational area within the drill site must not exceed 1000m2. Permit Environmental authority EPPR00585813

  89. F18

    Drill holes within the Endangered Regional Ecosystem and the 500m buffer of the Endangered Regional Ecosystems are to be a maximum of 200mm diameter.

  90. F19

    The construction of sumps within Endangered Regional Ecosystems or the 500m buffer of Endangered Regional Ecosystems must not exceed 10m2.

  91. F20

    Topsoil stripping within the Endangered Regional Ecosystems is limited to the sump area of 10m2.

    page 24Land and soil
  92. F21

    Topsoil stripping within the 500m buffer of the Endangered Regional Ecosystem is limited to an area no greater than 625m2 (with dimensions no greater than 25m x 25m).

    page 24Land and soil
  93. F22

    The environmental authority holder must minimize disturbance within Endangered Regional Ecosystems and the 500m buffer of Endangered Regional Ecosystems and avoid clearing mature trees. Tracks

  94. F23

    Any existing access and fence line tracks must be used.

  95. F24

    Any new tracks are to be constructed by linking naturally cleared or disturbed areas.

  96. F25

    Tracks are not to be constructed greater than 5m in width.

  97. F26

    Track construction involving blade clearing of established ground cover vegetation and/or clearing of mature trees is to be prevented or minimized.

    page 24Biodiversity
  98. F27

    Spacing of tracks must not be less than 250m.

  99. F28

    The environmental authority holder must minimise disturbance within the Endangered Regional Ecosystems and the 500m buffer of Endangered Regional Ecosystems and avoid clearing of trees.

  100. F29

    No clearing or disturbance for access to boreholes will take place within the Endangered Regional Ecosystems and the 500m buffer of Endangered Regional Ecosystems. Other land disturbance

  101. F30

    Rehabilitation of drill sites and sumps will be in accordance with the Code of Environmental Compliance for Exploration and Mineral Development Projects.

    page 24Rehabilitation
  102. F31

    Rehabilitation of areas disturbed within Endangered Regional Ecosystems and/or the 500m buffer of Endangered Regional Ecosystems must be completed as soon as practicable but no longer than 3 months after completion of the disturbance activity. Permit Environmental authority EPPR00585813

    page 24Rehabilitation
  103. F32

    The environmental authority holder must revegetate disturbed areas of Endangered Regional Ecosystems and the 500m buffer of Endangered Regional Ecosystems with native plant species endemic to the area that will promote the same vegetation type and density of cover to that of the surrounding undisturbed areas in the Endangered Regional Ecosystems and the 500m buffer of Endangered Regional Ecosystems. Schedule G - Regulated Dams

    page 25Regulated structures, Biodiversity
  104. G1

    The only regulated dam authorised under this environmental authority is the Flood Protection Levee. Certification and operation

    page 25Regulated structures
  105. G2

    Documentation required by the conditions in this schedule must be kept available for inspection by the regulating authority for a period of five (5) years after the conclusion of the environmentally relevant activity in respect of which this environmental authority has been granted.

  106. G3

    The holder of this environmental authority must not commence construction of a regulated dam unless: a) the holder has submitted to the administering authority two copies of a design plan, together with the certification of a suitably qualified and experienced person that the design of the regulated dam is fit for the purpose for that dam stated in that plan, and compliant in all respects with this environmental authority; and b) at least 28 days has passed since the submission of the design plan, or the regulating authority has advised the holder that the design plan is compliant with this condition.

    page 25Regulated structures
  107. G4

    When construction or modification of any regulated dam is complete, or within twelve (12) months of a dam becoming a regulated dam by virtue of a hazard assessment, the holder of this environmental authority must submit to the administering authority two copies of a set of `as constructed' drawings, together with the certification by a suitably qualified and experienced person that the dam `as constructed' is fit for the purpose stated in the hazard assessment and the design plan if the latter exists, and compliant in all respects with this environmental authority.

    page 25Regulated structures
  108. G5

    The holder of this environmental authority must ensure that there is always a current operational plan for each regulated dam, which may form part of other plans required by legislation.

    page 25Regulated structures
  109. G6

    The operational plan shall at least cover all matters relevant to the operation and maintenance of the regulated dam so that it is compliant in all respects with this environmental authority.

    page 25Regulated structures
  110. G7

    The holder of this environmental authority must ensure that, where a current operational plan covers decommissioning and rehabilitation, those operations are consistent with the objectives in any design plan for the dam. Annual inspection and report

    page 25Rehabilitation, Regulated structures, Monitoring and reporting
  111. G8

    The holder of this environmental authority must arrange for each regulated dam to be inspected annually by a suitably qualified and experienced person, in accordance with the following conditions. Permit Environmental authority EPPR00585813

    page 25Regulated structures
  112. G9

    At each annual inspection, the condition of each regulated dam must be assessed, including the structural, geotechnical and hydraulic adequacy of the dam and the adequacy of the works with respect to dam safety, and any recommended actions conveyed immediately to the holder of this environmental authority.

    page 26Regulated structures
  113. G10

    The holder of this environmental authority must immediately act upon recommendations arising from an annual inspection on condition and adequacy of a dam.

    page 26Regulated structures
  114. G11

    A final assessment of adequacy of available storage in each regulated dam must be based on a dam level observed within the month of October, accepted as valid by the suitably qualified and experienced person, and resulting in an estimate of the level in that dam as at 1 November.

    page 26Regulated structures
  115. G12

    For each annual inspection, two copies of a report certified by the suitably qualified and experienced person, including any recommended actions to be taken to ensure the integrity of each regulated dam, must be provided to the administering authority by 1 December.

    page 26Regulated structures, Monitoring and reporting
  116. G13

    The Design plan in accordance with condition G3 must include: a) drawings describing the location and dimensions of the levee and the mining excavations in the vicinity of the levee, including confirmation the levee meets the specified design requirements in condition G14; and b) a documented procedure for surveillance of the levee and any adjacent mining excavation slopes to detect and report to the administering authority any ground movement that compromises or may compromise the integrity of the levee.

    page 26Regulated structures, Monitoring and reporting
  117. G14

    Design requirements for the levee and adjacent mining excavation include: a) the design level of the levee crest shall be 0.5m above the predicted 2,000 year Average Recurrence Interval (ARI) event flood level. If the construction of the levee is staged, the level of the crest within those parts of the levee may be reduced to maintain a constant probability of overtopping. The risk of overtopping must not be greater than 2.5% during the life of the levee; and b) mining excavation slopes adjacent to the levee must remain stable and are to be designed with a factor of safety of 1.5 or above based on an accepted stability analysis.

    page 26Regulated structures
  118. G15

    The flood protection levee authorised under this environmental authority must be constructed and maintained such that: a) it does not result in erosion of the bank or bed of Roper Creek or Thirteen Mile Gully; b) it does not significantly impact upon riparian or existing remnant vegetation; and c) it will not erode during any flood events. Permit Environmental authority EPPR00585813

    page 26Regulated structures, Land and soil, Biodiversity
  119. G16

    The design specifications of the flood protection levee shall be determined by the predicted 1-in-2,000 year flood level, plus 0.5m and shall be provided with all design plans in accordance with conditions G3 and G4. Flood Protection Levee - Surveillance and Remedial Works

    page 27Regulated structures
  120. G17

    The condition of constructed levees including the surface area between the non-creek side of the toe of the levee and the endwall crest of the open-cut mining pit should be monitored for surface cracks and must at a minimum be inspected and assessed by a suitably qualified and experienced person at least once per year between the months of May and October inclusive (i.e. during the `dry' season and before the onset of the `wet' season), and at any time if alarming, unusual or otherwise unsatisfactory conditions are observed.

    page 27Regulated structures, Monitoring and reporting
  121. G18

    For each inspection, two copies of the surveillance report, including any recommendations for remedial works, must be provided to the administering inspection within twenty-eight (28) days of the date of inspection.

    page 27Monitoring and reporting
  122. G19

    Remedial works identified as being required for the flood protection levee during the inspections and assessments conducted under conditions G8 and G8, must be notified in writing to the administering authority within 5 business days of the completion of the inspections, and commenced within twenty-eight (28) days unless otherwise agreed in writing by the administering authority.

    page 27Regulated structures, Monitoring and reporting
  123. G20

    The annual return for this environmental authority shall be accompanied by a report, by a suitably qualified and experienced person, that certifies that the documented procedure for surveillance of the levee has been applied in accordance with the procedure, that there has been no erosion, cracking or vertical or horizontal deformation that has impacted on the integrity of the levee, and that the levee has been maintained in accordance with the certified design plan. Schedule H - Community Complaint Response

    page 27Regulated structures, Land and soil, Monitoring and reporting